Award of Merit Manufacturing: Ben & Jerry's Project Extra Chunk (BP01)
This $80-million fast-track expansion of a 20-year-old building was completed in 11 months, allowing the ice cream facility to increase production by up to 44%. Using a multiprime construction approach, seven contractors worked simultaneously on subprojects to expand eight areas of the manufacturing plant while keeping the existing facility in full production.